Question asked regarding 69-0714-503

Header information table
Letting ID: 21/12/21 Call Order: 018
Number: 2

Item 90

Can we get some clarification on the temp shoring? I am guessing it has to do holding the material under the approach.

Asked at 12/16/2021 01:22:59 PM


The temporary shoring is included to prevent the earth under the traffic lane from sloughing in during staged construction. This is noted in the General Notes on Sheet Number 2, along with additional notes and requirements for the temporary shoring.

Answered at 12/16/2021 04:48:10 PM

Error

Bid Express: New Roads

Bid Express: New Roads is a series of updates aimed at creating a more personalized experience that better caters to individual needs, jobs, and responsibilities.

Over the coming months, we'll be rolling out redesigned experiences to you across the entire service. Learn more.

Don't worry, if you don't love it, you can switch back to classic Bid Express for a limited time while you get used to the new look.

No thanks