Proposal T3667

LETTING LOCATION: Contracts Administration Office, POSTING DATES: 02/14/2018 and 02/28/2018 CONTRACT DAYS: 325 CONTRACT EXECUTION DAYS: 10 SPECIAL START DATE: N/A ACQUIS./FLEXIBLE START TIME: 15 Calendar Days The improvements under this contract consist of milling and resurfacing of the SR 8 (I-10) travel lanes and shoulders. Milling and resurfacing work includes the four ramps serving the interchange of SR 8 (I-10) at SR 77. Other improvements include ramp shoulder widening, replacement of the edgedrain system, guardrail construction, replacement of ditch pavement, installation of wildlife fencing, signing and pavement markings, and construction of a high tension cable barrier system in the median.
Proposal information table
Date Generated:12/20/2017Sections: 3
Date Revised: Amendments: 0
Call Order: 011 Highway Number: 6100
Items: 102 Counties: WASHINGTON
Project ID: D317135B

You must be logged in to view item data.